Garden Pictures 2017
An archive of the picture gallery from 2017. The oldest pictures are at the bottom of the page. At the bottom, time flows from left to right → → on any row but part way through [it is clearly marked] it switches to flowing from right to left ← ← on any row. Click on any picture to see a larger scale version. As you scroll down a 'return to the top' button will appear in the lower right corner of the screen.
Mid-November and the garden is really autumnal now although mild : the trees have not really shed all their leaves; |
By the end of Tuesday the doors were on and the roof trimming under way; |
Tuesday was a relatively miserable day but still OK for applying the roof membrane; the EPDM rubber sheet is glued down; |
By the end of Monday the roof is on the man cave; tomorrow will be tidying up and then the roof membrane can be placed; |
By early afternoon the basic structure is complete; we bought thye version with extra trusses; |
Monday and the work is soon under way; |
Sunday November 5 and preparation work - making the trusses - is under way for tomorrow's man cave erection; |
Early November and and the first phase of the rockery is finished; more stone is needed now; |
The strip foundations of the man cave are soon cast; of course, not every builder uses such high quality shuttering ... |
Monday October 30 and a new boys' toy is put to work; |
Some progress has also been made with the rockery as a delivery of horticultural grit was received last week; |
Sunday October 29 and it is exactly three weeks since sowing the lawn grass seed; |
As a result, River Pond [above the new dam] filled to the top of the lowest bricks; we can certainly go up two more courses and maybe four, it depends what happens above Chinese Bridge; |
Saturday October 21 was sunshine and [very heavy] showers; Winter Stream was a veritable torrent; |
This morning [October 19] an albino pheasant [AFAIK] came into the garden; it is too shy to take food - yet! |
48 hours after the last picture was taken : it is a bit like watching paint dry but the lawn grass shoots are definitely much longer; |
The same day, the foundations for the man cave have been excavated; |
Monday October 16, eight days after sowing, and a green tinge shows where the grass seeds have germinated and tiny shoots are appearing; |
That same weekend the nerines up at top pond were nearly in full bloom; |
Following a short break, the first weekend of October saw the lawn fully topsoiled and the grass seed sown; that is sand being added after to [hopefully!] fool the birds; |
Progress has been made on the future rockery too [and it is a good way of disposing of rubble from the lawn area]; |
Monday September 25 and the rest of the lawn has been composted and tilled plus last week's area has been covered in topsoil; |
That same day, the kit arrives for making a 'man-cave' to store the 'boys' toys'; |
Monday September 18 and the compost is laid on the first part of the lawn and tilled in; |
Mid-September and the nerines at top pond are in bud - but not the ones at entrance east [keep your fingers crossed]; |
During the week, the path from top pond to the well head was formed and partially made; |
That same day the levelling of the future lawn is completed and a delivery of 750 litres of straw compost is received; |
And here is that first pizza having survived been pushed onto the coals : it takes practice to use the peel correctly! |
The very first pizza about to be loaded into the oven; |
Monday September 11 and another red letter day : the oven is fired up for its first pizzas! |
On the Monday Damien is, among other things, busy levelling more of the future lawn; |
Still Saturday, September 2, and Dave has been busy down on Winter Stream throwing the first courses of the dam which will create the 'river pond'; |
There was also time to finish the rest of the Icelandic pebble path but not enough pebbles to do so! |
... and the first drying out fire was lit towards the end of the day : another red[hot] letter day! |
... and during the day was rubbed down with a wet sponge to finish it off ... |
Saturday, September 2, sees a push to finish the oven : the second [top] coat of render was applied in the morning ... |
Eddie also brought in sand, grids and pebbles to extend the path; hopefully it will be complete tomorrow; |
The same day, young Eddie [Damien's brother] came in to help tidy up; the log pile is complete and the log store under the pizza oven, as can be seen to the right, is full of smaller pieces; |
Friday September 1 and the arch shuttering [apparently called 'centering']could come down so the chimney was installed; |
Tuesday, August 29, and the first coat of the rendering - the scratch coat - is indeed done; [from here downwards a slight change in the flow of pictures, now left to right → → on any row] |
Bank Holiday Monday, August 28, is auspicious; we have not seen Phred the Pheasant for six months but today a young pheasant flew in : Son of Phred? |
Dave came out to build the pizza oven arch ... |
... and the remaining mortar was used to finish the quarry tile grouting and start the rendering; rendering will continue tomorrow; |
Meanwhile Damien focused on the rest of the Icelandic pebble path then started infilling between the future lawn level lines and developing the next one; |
Wednesday August 23 and the quarry tiles finally arrive; they are soon being laid around the core of the pizza oven ... |
... and work has started on level lines across what will become the lawn; |
Thursday and the waterproof cover is put on the oven; the remaining tiles have been fixed and yesterday's tiles grouted; |
The insulation is added the same day; the next step is to build the decorative brick arch at the front before the mortar weathering render is applied to the dome; |
Friday and the morning was used to finish the future lawn area then the machine was used to carry the boulders down to the future rockery ... |
... which went remarkably well to the extent that the boulders were placed into position too; the rockery will be to the right of the path heading down to the 'Chinese' bridge; |
This view shows the bank along the western fence where another sleeper wall will be built; the just mortared pizza oven [see below] is also seen; |
As the work wound down towards Friday evening it was finally possible to get a picture of our driver who had worked the digger so well all week - and what a week it was! |
Wednesday night and early Thursday were wet again so there was danger of bogging down on Thursday; this shows the track of the dumper taking surplus clay to the glebe land where the carpets have been lifted in preparation; |
However, by the end of the day the future lawn was starting to take shape; there is still some excavation to do tomorrow though as there needs to be room for top soil; |
The sandstone pavers for the patio and well head were also delivered today; this is a trial fit; they are said to be 'Golden Fossil' but we haven't seen any fossils! |
Some reinforcing was applied to the joints of the pizza oven, ready to be mortared on; |
Wednesday was drier but work continued on the future lawn area, over-cutting to allow topsoil to be added back ... |
... and the concrete around the base of the oven was cast; everything is now ready for the quarry tiles; |
At the end of the day the clay mountains around the oak were gone and the vista to the 'Chinese' bridge opened up [ignore the mound of top soil for now]; |
This is a view of the future river pond; the orangey clay dumps are dry and powdery but once wet it should be possibly to create the 'river banks'; |
Tuesday August 15 and overnight rain meant that water accumulated in the bed of Winter Stream so the digger cleared the future lawn area ... |
... which exposed an elephant hawk-moth caterpillar; it was about 80 mm long with its 'trunk' extended; |
At the pizza oven, the sealant was applied to the match faces and each front half was offered up in turn ... |
... and hey presto : the basic oven is complete; the next step is to concrete in around the base of the oven to finished level ready for quarry tiles; |
Monday August 14 and what a day! the boys' toys are soon in action : the work starts recovering the lovely top soil from the bed of Winter Stream where the dam will be ... |
... and by the end of the day there are two piles of that and half the clay mountains around the oak have been levelled, pushing them down into the valley; |
That doesn't mean work has stopped on the pizza oven : the rear dome is man-handled up onto the base ... |
... and the refactory floor is laid; hopefully the front half-domes can be installed tomorrow; |
Early August and work has started on the permanent log store ... |
... and it is a good job the scrap metal merchant hasn't appeared as these two pieces of the old water tank make good log retainers; |
Friday August 11 and the very serious 'boys' toys' arrive, ready for next week's landscaping work; |
Mid-August and anything van Gogh can do ... [ear ear I hear you say]; |
Still Monday July 31 and the final ~100 kg of iris is removed from black pond [what looks like a black mass in the pond is actually clear water with the sky reflected in part]; |
This view, from the same day, shows the contoured earth around the well head; that is an aconite [Aconitum napellus 'Spark's Variety'] in the foreground; |
Friday August 4 and the kit for building the pizza oven arrives; every piece of the 'igloo' is heavy and the semi-dome particularly so; |
Monday August 7 and the concrete slab under the pizza oven has been laid together with the oven base; the bed behind the dwarf wall has also been finished; |
Also Monday July 31 and Dave, having progressed as far as possible inside, starts work on the dwarf wall of the patio in mid-afternoon ... |
... and ninety minutes later is already laying the block inner skin; |
The top course is 'brick on end', sometimes called a rowlock course for reasons lost in antiquity; |
This is the view at the end of the day with the wall complete; |
Tuesday July 25 and today's project task [as distinct from maintenance such as weeding and clearing] is to shutter the slope by the kitchen window ... |
... and Wednesday's task is to pour it; the addition of black pebbles was a last minute thought : they will have a light hosing this evening; |
Monday July 31 and the strawberry tree [Arbutus unedo] given to Win by the staff on her retirement is planted in the home garden; he is christened Mícheál ... |
... and the area next to the slope is tidied up to cope with the drop in level of the DPC; |
Monday July 24 and the foundation trench for the retaining wall is completed - including repairing the drain discovered damaged by the 2016 builders; |
It was then down to black pond where maybe another 100 kg of iris was removed; once that has drained down we can tackle the last of it; |
The same day Dave, having finished the dining room fireplace work, laid the last of the bricks for the pizza oven base ... |
... and this is the view [from the orangery roof!] of the work; note that the retaining wall foundations are complete too; |
Monday July 17 and the concrete soffit of the wood store / footing of the remaining brickwork was soon complete [and the herb bed was filled with soil]; |
Damien - having helped with clearing another 100 kg of iris down at black pond - then started work on the foundations for the retaining wall; |
Friday July 21 and the braai is complete : the outer stainless bars are cut and the herb bed is planted up [with thyme, chives and marjoram]; |
Saturday is a red letter day; as ou'ma would say : the proof of the braai is in the eating; |
Saturday July 15 and by mid morning the brickwork around the well head is complete ... |
... so Dave started on the brickwork above the lintel for the pizza oven side; |
That too was complete by lunchtime; Dave then moved on to the north side brickwork [nearer the camera]; |
This picture was taken on Sunday morning after the shuttering for Monday's concrete work was complete; it shows the 'table' to the right of the braai and the 'herb bed' to the left; |
Saturday evening and a great spotted woodpecker is hunting on Sue's oak next door; this was taken with maximum optical zoom and then high electronic zoom; |
Wednesday July 12 and time to finish the well head concrete; by 10:00 the concrete was complete to the level of the existing concrete ... |
... and by 12:00 the screed topping was complete too; that clears the way for more brick laying on Saturday; |
July 13 and work starts on the rescue of black pond, almost completely choked by the native water iris Iris pseudacorus [commonly called 'yellow flag']; judging by the work so far there must be a total of 3 to 500 kg [wet] of the plant in the pond; |
Saturday July 8 and strip footing cast yesterday by the well top is ready for bricklaying; |
The log store under the pizza oven is soon up to level and work starts around the well head; |
Later in the day attention turns to the braai; |
This is the result at the end of the day [now after three days bricklaying]; there is a lot of back-filling and shuttering required next so don't expect the same progress! |
Still Saturday and later in the day the focus turns to the pizza oven side; |
This is the result at the end of the day [after two days of bricklaying]; next week will [hopefully] see the braai firebed cast and the concrete around the well; |
Monday July 3 and the firebed is cast; it will have to be kept wet all week if the sun continues to shine; |
The next day and large grey pebbles are used to fill the mini-bed at the orangery and planted up with four types of sedum; the pebbles continue to the sleeper to stop cats digging up soil onto the path; |
Late June and the step has been cast at the brickwork; the next course of bricks has been placed just to get a feel of the finished look; |
The missing 150 high sleeper has also been installed so the sleeper work is fully complete; |
Saturday July 1 and another day of brickwork; the bricks around the step and at the sleepers are soon finished ... |
... and not long after the lintel for the fire bed of the braai is in place; |
June 16 and, with flowering over, the serious pruning of the first big rhododendron on the eastern border was completed; the front half of the right-hand one was also pruned but its big cut must wait a year; |
The setting out of the braai bricks was done on Sunday June 18 but unfortunately the brickie [who has the laser level] was a no-show; we may have to break out the old water level hose ... |
Thursday June 22 and Dave the brickie is here setting out for real [with mortar]; |
The end of the day shows very satisfactory progress; next stage is to cast concrete at the well before brick work can resume; |
June 12 and the objective is to cast the foundations for the barbecue area next to the [future] patio ... |
... and work was soon progressing at speed thanks to Ian's mixer [a.k.a. boys' toy II] which he has kindly lent us; |
By 15:00 the objective was achieved [albeit with some substitution of Type 1 aggregate for ballast and fine sand for builders' sand] ... |
... and there was still time to plant the Alchemilla mollis from Chelsfield along the south bank of Winter Stream; |
By the end of May the bed under the cherry tree had [finally!] been recovered from the rampant growth and weeds; |
In early June some reclaimed rocks were delivered with material for the dining room fireplace; they are for a rockery where the home garden drops down to the glebe land; |
Still early June and the edge of the mainly shade bed in the north west of the glebe land is starting to take shape ... |
... and the bed on the south side of Winter Stream is looking good after a lot of effort with the 'boys' toy'; |
Later in May and the magnificent weather has brought the garden on; the east entrance bed has now been reclaimed as far as the cornus [does anybody want perhaps a thousand muscari bulbs?] ... |
... and close by the medlar [Mespilus germanica, a Christmas present from young Mike] has been planted in the meadow; |
Progress has been made round at the future patio, digging the foundations for the braai and pizza oven ... |
... and down in the glebe land the red astilbes - which really enjoy the damp conditions - have been joined by some white ones called 'Cappuccino'; |
Mid-May : back from travels to find that the rhododendrons on the east border are flowering [the paler lilac mist to the right is the wisteria that has run wild] ... |
... and the iris moved from the garage door has flourished; that is a Siberian iris closer to the camera on the left, a definite objet trouvé; |
Damien is soon hard at work with the new toy, tilling the kitchen garden ... |
... but the toy struggles at the back where the ground is essentially clay sub-soil never previously cultivated; perseverance will be needed; |
Tuesday May 02 : the first sleepers along the east side of the entrance are now in place [and the cleaning up of the bed has reached the mass of grape hyacinth, now finished flowering] ... |
... and a herb garden on the west of the house has been planted out between the bedding plants; |
Monday May 8 : Mike may be in the Far East but work continues; here the black pebbles have been put down at the orangery ... |
... and here the excavation where the braai and well head are to go is under way; |
Monday April 24 : the top layer of sleepers is complete; the hardcore of the path up to the well is also down; [what you don't see is that the thick middle layer sleeper is missing with temporary props standing in]; |
We are down to a choice of two pebble types for the paths : Scottish on the left and Icelandic on the right; |
Meanwhile, out at the entrance, the east bed has progressed another metre or so and work has started on the sleeper border on that side; there is a lot of building rubble in the bed; |
Friday April 28 was 'Boys' Toys' day : not much work done in the house! |
Easter 2017 and progress has also been made with the sleeper wall on the west side of the house; |
This view is from the dining room window; |
Two days later and the drain along the route of the path is complete ... |
... and two more sleepers have been 'chainsaw carved' to shape and installed; we need to find a thick sleeper from somewhere to finish the middle layer; |
April 10 and the gravel bed around the pond is finally finished : no more gravel washing! a teak bench has been installed next to the path looking across the pond to the house and the [future] patio beyond; |
Meanwhile, the outline of the future south lawn has been extended; the clay soil is heavy going so a tilling machine is needed; |
One gets a better view from bedroom 2 above [the view from the master bedroom being hidden by the orangery lantern]; |
The east path and mini-patio outside the French doors were complete in time for Easter; the two olives have been potted on; |
Still early April and it might look a mess down on the eastern boundary next to black pond but that is actually a bonfire's worth of old and diseased Cornus; by Easter all will be plain to see; |
The triangular bed in the glebe land recovered nicely from last month's weedkiller; two Persicaria microcephala 'Red Dragon' and a Dierama igneum have been brought down from Chelsfield; |
The south bank bed of Winter Stream also recovered well from the weedkiller but some weeds were missed so a second application was needed; |
At the orangery the pathway and associated bed has also progressed but it took a tote bag full of aggregate in front of the orangery doors : two more bags are on order; the winter pansies reflect the name of the new room nicely; |
Monday March 27 and the clocks went forward over the weekend : that has woken the cherry up! |
We have got back to that pathway as noted below and the first 3 m2 are complete, awaiting the final choice of infill; |
Early April and the weather has favoured gardening; the path at top pond is nearly complete ... |
... and the the bed under the cherry [which makes good shade cover for tender plants] is slowly coming back from weediness; |
Also on the spring equinox and the refurbishment of the gravel path around the pond is complete [but not the path leading to it!]; ... |
... while under the cherry tree some primroses have been planted next to the cyclamen; |
A start has also been made on marking out the eastern bed of the south garden - but we need to get back to that pathway which will run past the orangery; |
A casual observer will not see the changes in the glebe land but another 14 young [and diseased] oaks have been thinned out and the weed mass to the south of the stream has been sprayed even if the results are not yet obvious; |
Mid-March and the kitchen garden has been tidied up a lot [this view is from the dining room window] ... |
... and the south end of the western path is close to final depth next to the well; |
The spring equinox and the Magnolia stellata named for and planted by Tony de Joux last year is looking lovely, as is the Acer palmatum 'Katsura' just coming into leaf; |
The proof of the March 12 comment [just below] is now there for all to see in the east entrance bed; |
February 23 and the first daffodil is out in the west entrance bed ... |
... and the hellebores are out in the same bed closer to the main entrance; |
March 11 and spring is really here; perhaps this close-up will help confirm that; |
The next day and time to start planting up the east entrance bed; most of the greenery further down is grape hyacinth [Muscari] plants, not weeds; |
On the same day as below the spring is to be seen gently adding to the flow of Winter Stream ... |
... and one of the many robins in the garden waits for a titbit to appear among the gardener's work; |
Three days later - still mid-February - and the crocuses are out in all their glory under the Rhus next to the cherry tree ... |
... and so are the cyclamen [this time C. coum] under the shrubs by the entrance gate : spring is just around the corner; |
Also in the glebe land, the area around the oak where we dream of a future lake has been cleared of the weak saplings struggling to grow; |
The weather was good enough to cut back the concrete and steel sheets at the head of the well; next step is to cast a neat edge to the concrete cap; |
Mid-February and a lovely sunny, cold Monday; snowdrops are flowering under the cherry tree ... |
... and the hazel catkins catch the sun; |
More disruption by [paid] work but John the gardener has carried on; the top pond gravel is proceeding at a pace although it is tedious, washing the existing gravel and blending with new; |
The east bed at the entrance has now been stripped bare to lie fallow over winter - which is now upon us; |
January 2 2017; yesterday's rain meant that the dam at Willow Pond finally spilled over; it is pleasing to see in the close-up that the dam is indeed level; |
The weather today is in marked contrast to New Year's Day : the catkins on one of the willows in the glebe land are starting to appear; |