Welcome to Peasmarsh Old Rectory
- a mid 16th century frame house hidden by 1930's skin.
TOR Logo
THE OLD
RECTORY
PEASMARSH

Garden Pictures 2018

An archive of the picture gallery from 2018. The oldest pictures are at the bottom of the page. Time flows from right to left ← ← on any row. Click on any picture to see a larger scale version. As you scroll down a 'return to the top' button will appear in the lower right corner of the screen.

picture picture picture picture
Many of the plants were dormant and just don't show at the moment; these various Heuchera selections under the oak tree do show though;
 
December 17 was an epic planting day with close to 90 plants planted [thanks to Rob]; this is pachysandra terminalis for ground cover;
 
December 7 was not so much a red letter day as a 'red cap' day when a green woodpecker came to visit the wildflower meadow; the close-up is very grainy;
 
This picture was taken on November 22 after things had subsided; the dam is intact but no longer upright so back to the drawing board [and cement mixer in 2019];
 
picture picture picture picture
Back in August the River Pond dam had been increased in height; the first real rains were on November 11 when Winter Stream was a torrent : the dam was pushed over by water pressure!
 
This is with the new liner roughly in place and the filling - pumped from the well - under way; shortly after this was taken, Mike's L femur snapped, dumping him in the pond;
 
85 fish were removed and stored in two large buckets; no sign of any newts but lots of water boatmen;
 
October 15 - a fateful day- and it is time to change the liner of top pond; this is as the pond is getting low, the liquid is mainly mud;
 
picture picture picture picture
Mid-October and two of the new cyclamen - a gift from Marilyn and Tony - nestle under the new rocks in the rockery;
 
Two days later and the new rocks can be seen in a better light after the soil has been prepared and top dressed; the grit will weather down in due course to match the existing;
 
The same day and the new rocks are roughly placed at the top of the rockery; just need to finalise, add grit to the soil and top dress with grit;
 
October 1 and the north bank of Winter Stream is rotavated to level off the clay layer we added, mix in ash and suppress weeds;
 
picture picture picture picture
September 27 and the remaining rocks required for the rockery have arrived; hopefully a job for Monday;
 
Late September and the asters [Symphyotrichum if you must] beyond Top Pond are striking in the autumnal sunshine; no wonder they are called 'September Rubin' [Ruby];
 
How can one be so blind? walk past the nerines several times each day but only see the first bud when almost ready to pop; autumn is coming!
 
Mid-September and the wild rose by the driveway is offering a magnificent display of hips;
 
picture picture picture picture
A single tree has been left; once it has dropped its leaves it will be reduced in height by about one third and will hopefully recover fully;
 
Also the 10th and the tangle of Rhus in the wildflower meadow is being removed;
 
September 10 and a future hedge of Japanese holly [Ilex crenata] is planted along the one edge of the deck;
 
Early September and the autumn crocuses [Colchicum autumnale] planted in the shade of the deck oak are flowering [the leaves come later];
 
picture picture picture picture
The same day, the work to clear the weedy mass in Winter Stream continued; a few more hours of work and it should be possible to recover the silty top soil;
 
Friday and the dam for the future River Pond is completed to the existing level and then built up another course; now we have to wait and see what water level results;
 
This is the view of the deck from the top of the Chinese Bridge; it took 11 days of far from continuous work start to finish;
 
Thursday August 23 and the deck is complete, albeit with some screws still to be inserted in the planking and something to be done with the hole behind the tree;
 
picture picture picture picture
On Wednesday the plank straightener arrived so, after the secondary fixing and again with Ben's help, the first six planks were laid and fixed;
 
The next day, with Ben's help, the structure was completed with all members secured in place; a little bit more secondary fixing and it will be ready for planking out;
 
On the same day the hedge was finished : no more cutting for 12 months;
 
Monday August 20 and the last post is installed so the structure can now be finished; all joists have been cut and placed but not yet secured;
 
picture picture picture picture
Down on Winter Stream and clearance of the weedy section is underway; some of the marigold [Caltha palustris] has been saved and re-planted, as has some of the native flag [Iris pseudacorus];
 
Saturday August 18 and the deck has advanced well although the joists are only trial fit, as are the two planks;
 
The lobelia 'Queen Victoria' has been flowering away down by Black Pond for a month now and shows no sign of letting up;
 
August 14 and with the help of Inky two intermediate posts plus part of the intermediate beam are installed and concreted in;
 
picture picture picture picture
Much more mundane but a start is also made on the annual trim of the beech hedge today - until rain stops play;
 
The basic shape is in place and the corner posts concreted in by lunchtime; hopefully the frame will be completed next Monday;
 
Monday August 13 and work starts on the erection of the deck;
 
Also August 7 and the timber for the deck to be erected under the oak has been delivered : perhaps make a start next week? the path [yellow brick road?] has now been wetted and compacted;
 
picture picture picture picture
August 7 and the pathway down the side of the house from the patio has been started;
 
The same day, the self-binding gravel path is essentially complete although it still has to be wetted and compacted;
 
The paving is soon finalised; the pointing, as with the patio, will have to wait for another day; then we can build the [circular] well wall;
 
July 28 and Dave finally gets to work on the rest of the well head;
 
picture picture picture picture
July 24 and two bulk bags [~1.7 tons] of self-binding gravel have been delivered; work starts immediately on the final approach to the Chinese bridge;
 
Still mid-July and we have found some orchids in the north east corner of the glebe land; we think that they are the green-flowered helleborine, Epipactis phyllanthes; the flowers hang down so are difficult to photograph, this is the best one can manage;
 
Mid-July and the patio paving is complete other than the pointing [which will be done when the well top is also finished];
 
July 9 and the last rhododendron plus the golden laurel on the eastern boundary were [finally] brought under control; the mulching can wait for another day;
 
picture picture picture picture
Sunday July 8 and it is Peasmarsh Open Gardens day! we opened the garden not for people to see a magnificent garden but to see the project at 30% complete [if we finish on time!];
 
The next day, once the bed had cured, allowed the filling-in around the edges of the laid paving to show the final effect [just imagine the pointing!];
 
The first of the pavers were also laid on the well top;
 
At the end of two days about two thirds of the Indian sandstone pavers were laid; the slow progress was because of the amount of bedding mortar needed;
 
picture picture picture picture
Early July and back from more travels; Dave the brickie was suddenly free for two days so we started the patio;
 
June 19 and a moorhen has been visiting under the oak at the end of the home garden so near what will become River Pond; unfortunately the camera insisted on focusing on the tree trunk;
 
Mid-June and back from travels; the sleeper wall is slowly being planted up and the annual lobelia planting above is looking good;
 
May 21 so one month to the solstice and the irises up at top pond are looking lovely; the stone surround of the pond is up in preparation for changing the [leaking] liner;
 
picture picture picture picture
May 20 and the new grass seed under the cherry has sprouted; it is 8 days from sowing;
 
The end of day view from the patio end; next task is to sort out the bed next to the wall;
 
By the end of the day the back-filling is well advanced [but will need filling up as it settles with time] and the area tidied up;
 
May 14 and the sleeper wall along the lawn is complete and the space behind is being back-filled;
 
picture picture picture picture
Mid-May and the uneven grass area under the cherry tree has been back-filled and re-sown : watch this space!
 
May 10 and the final portion of the lawn edge has been completed; the bed is only 300 wide so it may be paved;
 
A clematis purchased last week and planted down by the eastern border fence is now flowering : hopefully a sign of things to come;
 
May 7 and the sleeper wall is progressed further, including the first two sleepers of the top course; the spacers between courses 2 and 3 will allow planting pockets for hanging plants;
 
picture picture picture picture
The same day and the first of the sleepers for the retaining wall on the west side were also in place; the edging here, close to the sleepers, has still to be finalised, probably after the wall is finished;
 
May 3 and the last of the sleepers along the east of the formal garden is in place; the lawn edging on this side can also be clearly seen;
 
Phred the Pheasant may be Dead Phred but his successor seems to have raised two chicks, seen here early evening on April 30 after a very wet day; one looks to be colouring up as a male, the other female;
 
April 14 was a wonderfully sunny day so the new lawn received its first ever haircut; thin and bare patches were over-sown the following day after which it rained : just perfect timing!
 
picture picture picture picture
March 13 and part of today was spent pruning the remainder of the old apple tree [the rest was pruned in late winter 2016 and 2017];
 
Architectural gardening has started again : this is the sub-base for the sleeper wall along the west bounday, the sleepers having just been delivered; the new lawn has also been raked clear;
 
The first full week of March and last week's extreme cold is a distant memory; a patch of crocus seems to have come through the freeze unscathed;
 
Snow hides all of the ugly bits and shows off the garden [not quite to perfection yet!];
 
picture picture picture picture
The last day of February 2018 and the garden was coming to life - until the cold air blew in from Siberia; sunrise across the snowy fields was magnificent;
 
The same day, the clay banks at River Pond dam were brought up to current brick level; the water is now under the Chinese bridge but we can go up at least one more course;
 
Monday November 27 and the screed top is cast on the man cave floor;
 
November 21 and the first part of the man cave floor is being cast; next week - if the weather holds - will see the screed cast on top;
 

 


MW Logo